Chubu Electric Power Co.,Inc. | Major Power Source Development Plan - Mid-Term Outlook

Mid-Term Outlook Major Power Source Development Plan

Internally-generated Power

(MW)

Type FY2017 (Actual) FY2018 FY2019-FY2022 FY2023-FY2027
Nuclear Does not apply Does not apply Does not apply Does not apply
Thermal Nishi-Nagoya Unit 7
(September 2017, March 2018)
(2017/9, 2018/3)
2,376

Yokkaichi Unit 1,2
(December 2017) (2017/12)
-440

Atsumi Unit 1
(December 2017) (2017/12)
-500
Owase Unit 1,3
(FY2018)
-875

Yokkaichi Unit 3
(FY2018)
-220
Taketoyo Unit 5
(March 2022) (2022/3)
1,070
Does not apply
Hydro Shin-Okuizumi
(March 2018) (2018/3)
0.32

Existing hydroelectric power stations
9 locations (*1)
(FY2017)
8.44
Does not apply Seinaiji
(June 2022) (2022/6)
5.6

Abekawa
(December 2022) (2022/12)
7.1

Kurokawadaira
(FY2021)
0.17
Does not apply
Renewable energy
Wind
Does not apply Does not apply Does not apply Does not apply
Renewable energy
Solar
Mega Solar Kawagoe
(May 2017) (2017/5)
7.5
Does not apply Biomass power generation facility at Yokkaichi
(April 2020) (2020/4)
49
Does not apply

(Note 1) Facilities for which the date of commencement of operation is undecided are not included.
(*1) Output increase from facility improvement, etc.