Transportation (Return) of New Fuel from Hamaoka Nuclear Power Station Reactor No. 1 Completed

January 17, 2013
Chubu Electric Power Co.,Inc.

This is to announce that, in keeping with our decommissioning plan for Hamaoka Nuclear Power Station Reactor No. 1, we have returned new fuel that had been in storage at the reactor's new fuel storage facility. Details of the fuel's return are below.

1. Period of transport  

Wednesday, January 16, 2013

2. Route of shipment

Hamaoka Nuclear Power Station - Global Nuclear Fuel-Japan Co., Ltd. (Yokosuka, Kanagawa Prefecture)

3. Quantity shipped

New fuel assemblies (Uranium fuel): 96  (in 48 shipping containers)

4. Mode of transport

Land transport

Attachment

Attachment1

Reference

Overview of shipping containers used for shipment

Model

Weight of shipping containers*1

Length

Width

Height

RAJ-II

Approx. 930 kg

Approx. 507cm

Approx. 73 cm

Approx. 74 cm

*1:Weight without fuel assemblies

Fuel assemblies were shipped in shipping containers meeting the technical standards prescribed by law.

Global Nuclear Fuel-Japan Co., Ltd. is the owner of the shipping containers.

Future shipping plans

As announced on September 21, 2012 and December 13, 2012, all FY2012 transportation of new fuel, including return of new fuel assemblies, has been completed with this shipment.

Detailed plans for FY2013 shipments will be finalized following consultation with all parties concerned.