Chubu Electric Power would like to announce plans to construct a regular water-flow release hydroelectric power station directly below the Yahagi No. 2 Dam, which is owned by Chubu Electric Power. The new power station will utilize both dam head and water release for power generation.
Chubu Electric Power has been continuing to develop renewable energy in the light of diversifying energy sources and addressing the problem of global warming.
In line with these goals, we have decided to construct Shin-Kushihara Hydroelectric Power Station, a regular water-flow release hydroelectric power station with 220 kW generating capacity, directly below Yahagi No. 2 Dam. Operation is planned to begin in FY2015.
As we proceed with development work, we shall be grateful for the understanding and cooperation of the local authority and local residents.
For the future, Chubu Electric Power will engage in continuing development of conventional and regular water-flow release hydroelectric power, a renewable energy source that promises stable electricity output. Also, to increase output and electricity production, we are making systematic improvements to existing hydroelectric power station facilities.
[Overview of plan]
Name of station |
Shin-Kushihara Hydroelectric Power Station |
---|---|
Location |
Kushihara Oyana, Ena City, Gifu Prefecture |
Name of dam |
Yahagi No.2 Dam |
Generating Capacity |
0.22MW |
Projected annual electricity output |
Approx.1,700 MWh |
Reduction in CO2 emissions |
Approx. 900 tons per year |
Construction work planned to start in |
FY2014 |
Entry into service planned for |
FY2015 |