Changes in the Transport Schedule for New Fuel, etc. for FY2014 at Hamaoka Nuclear Power Station (Second Round)

October 14, 2014
Chubu Electric Power Co.,Inc.

Chubu Electric Power's transport schedule for spent fuel announced in the "Transport Schedule for New Fuel, etc. for FY2014 at Hamaoka Nuclear Power Station" on March 31, 2014, has been changed as follows.

 

[Transport schedule after the changes]

Spent fuel 

Power plant name Quantity shipped Period of shipment

Receiving facility

 Hamaoka Nuclear
 Power Station

 NFT-12B x 1  package
(11 assemblies, about 2 ton U)

 Fourth quarter

 Japan Nuclear Fuel Limited
 Spent Fuel Receiving and
Storage Facility  

[Transport schedule before the changes]

Spent fuel 

Power plant name Quantity shipped Period of shipment

Receiving facility

 Hamaoka Nuclear 
 Power Station
 NFT-12B x 1 package
(11 assemblies, about 2 ton U)

 Third quarter

 Japan Nuclear Fuel Limited 
 Spent Fuel Receiving and
Storage Facility 

Although we plan to transport the spent fuel in Hamaoka Nuclear Power Station Unit 5, as a result of the process adjustment of the nuclear reactor inspection work and transport preparatory work, etc., related to seawater infiltration event at Hamaoka Nuclear Power Station Unit 5, the transport period has been changed from the third quarter to the fourth quarter.