Press Release
Changes in the Transport Schedule for New Fuel, etc. for FY2014 at Hamaoka Nuclear Power Station (Second Round)
October 14, 2014
Chubu Electric Power Co.,Inc.
Chubu Electric Power's transport schedule for spent fuel announced in the "Transport Schedule for New Fuel, etc. for FY2014 at Hamaoka Nuclear Power Station" on March 31, 2014, has been changed as follows.
[Transport schedule after the changes]
Spent fuel
Power plant name | Quantity shipped | Period of shipment |
Receiving facility |
---|---|---|---|
Hamaoka Nuclear Power Station |
NFT-12B x 1 package |
Fourth quarter |
Japan Nuclear Fuel Limited |
[Transport schedule before the changes]
Spent fuel
Power plant name | Quantity shipped | Period of shipment |
Receiving facility |
---|---|---|---|
Hamaoka Nuclear Power Station |
NFT-12B x 1 package (11 assemblies, about 2 ton U) |
Third quarter |
Japan Nuclear Fuel Limited |
Although we plan to transport the spent fuel in Hamaoka Nuclear Power Station Unit 5, as a result of the process adjustment of the nuclear reactor inspection work and transport preparatory work, etc., related to seawater infiltration event at Hamaoka Nuclear Power Station Unit 5, the transport period has been changed from the third quarter to the fourth quarter.