Chubu Electric Power would like to announce that through arrangements with parties concerned, the Company finalized the timing to transport low-level radioactive waste. Amongst the matters announced on March 30, 2016 as "Transport Schedule for New Fuel, etc. for FY2016 at Hamaoka Nuclear Power Station," Chubu Electric Power had been postponing the timing to ship the waste.

[Changed transportation schedule]

Low-level radioactive waste

Power plant name

Quantity shipped

Period of shipment

Receiving facility

Hamaoka Nuclear Power Station

Transport containers:80
(640 drums)

January 2017

Japan Nuclear Fuel Limited
Low-level radioactive waste Disposal Center

[Planned transportation schedule]

Low-level radioactive waste

Power plant name

Quantity shipped

Period of shipment

Receiving facility

Hamaoka Nuclear Power Station

Transport containers:80
(640 drums)

Timing undeterminded

Japan Nuclear Fuel Limited
Low-level radioactive waste Disposal Center

The low-level radioactive waste transportation for FY2016 was originally planned to be carried out in June this fiscal year, but Chubu Electric Power postponed the shipment (timing undetermined). This was a result of a failure in a ceiling crane, located in the low-level waste management building of Japan Nuclear Fuel Limited's Low-Level Radioactive Waste Disposal Center.