Press Release

Press Release

On the Construction Plan for the Atsumi Wind Power Station (tentative name)

December 11, 2018
Chubu Electric Power Co.,Inc.

Chubu Electric Power has decided to construct the Atsumi Wind Power Station on the Atsumi Thermal Power Station premises in Tahara-shi, Aichi Prefecture today.

The Atsumi Wind Power Station (tentative name) will be a wind power station with a maximum output of 7400 kW. Preparation work will begin in FY2019 before the start of full-scale construction in FY2020 and the start of commercial operations in FY2021.

We will go forward with developing this project with the cooperation and understanding of the local municipality, the local community and related parties.

Chubu Electric Power will continue to actively work on introducing energy sources with low CO2 emissions, including the development and introduction of renewable energies such as wind power and solar power generation in order to realize a low carbon society.

[Plan Overview]

Station name 

Atsumi Wind Power Station (tentative name)

 Location

Tahara-shi, Aichi prefecture (on the premises of Atsumi Thermal Power Station)

 Maximum output

7,400kW (2 Units)

 Estimated annual electricity generated

Approx. 19 million kWh(amounts to the annual electric power consumption of approx. 6000 ordinary households)

 Amount of CO2reduced

Around 9000 tons annually

 Scheduled construction start date

FY2020

 Commercial operation start date

FY2021

[Location of project area]

Location of project area of picture

Go to the Top of the Page