Press Release Back Number(2005)

Revised schedule for transportation of new fuel for the Hamaoka Nuclear Power Plant in FY 2005

December 22, 2005
Chubu Electric Power Co., Inc.

Chubu Electric Power made the following changes in the schedule for the transportation of new fuel for the Hamaoka Nuclear Power Plant in FY 2005.
In response to requests from Nuclear Fuel Industries, Ltd., the manufacturer of the fuel, which had hoped to transport fuel earlier due to reinforcement work on their plant facilities, we have rescheduled the transportation of new fuel for Reactor 3 at the Hamaoka Nuclear Power Plant from FY 2006 to the fourth quarter of FY 2005.


The transportation of new fuel for Reactor 4 at the Hamaoka Nuclear Power Plant, scheduled for the third quarter of FY 2005, was successfully completed on October 27-a fact we previously communicated to you on the same day.


New schedule

Name of power plant Reactor 4 at the Hamaoka
Nuclear Power Plant
Reactor 3 at the Hamaoka
Nuclear Power Plant
Amount transported 184 pieces 116 pieces
Time transported Third quarter Fourth quarter
Shipping facilities Global Nuclear Fuel Japan Co., Ltd. Nuclear Fuel Industries, Ltd.

Previous schedule

Name of power plant Reactor 4 at the Hamaoka
Nuclear Power Plant
Amount transported 184 pieces
Time transported Third quarter
Shipping facilities Global Nuclear Fuel Japan Co., Ltd.