Concerning Commissioning of the Technical Consulting Operation in Singapore
January 18, 2007
Chubu Electric Power Co., Inc.
On this occasion, SP Power Grid Limited of Singapore (hereinafter called "SP PG LTD", an electric distribution company, has entrusted our company with the consulting operations relevant to technical audit of the power transmission lines and substation installations.
The company shall provide advice / instructions from the viewpoint of quality control for the underground transmission lines to supply electric power to Singapore Marina district including the integrated resort installations under development and the construction of substation project of SP PG LTD.
In addition, we shall provide technical advice and instructions for the inspection / installation of construction work on site and at the plants of the equipments' manufacturers in relation to the general construction work of the power transmission substation installation implemented consistently by SP PG LTD.
Our company is looking forward to expand even more its relation with SP PG LTD by implementing new cases relevant to these current power transmission lines and substation installations.
1 Content of Commissioned Operations
(1) Commissioned Matter
Technical audit concerning the power transmission lines and substation installations Power Grid Limited
(2) Execution Territory
Republic of Singapore
(3) Execution Period
From January 2007 to March 2009 (27 Months)
(4) Principal Execution Content
< Underground transmission lines to supply electric power to the Territory including the general resort installations and the construction of substation project >
Advice/ instruction in quality control and inspection and suchlike concerning the purchase of equipment
< General construction work of the power transmission substation installation implemented consistently >
Technical advice and instructions for the inspection/ installation of construction work on site and observing the inspection at the plants of the equipments' manufacturers
2 Backgrounds to the Current Commissioned Matter
The electrical system of Singapore is hidden underground and is highly reliable and greatly contributing to the development of the country.
PG LTD is scheduled to improve even further the electric power quality and the system reliability in the future, and PG LTD has entrusted our company, which has been continuously providing consulting services and suchlike concerning the maintenance technology of the power transmission substation installations of said company, with the current matter.