Chubu Electric's schedule for transporting new fuel, spent fuel and low-level radioactive waste at the Hamaoka Nuclear Power Station is as follows.

The schedule of these shipments is subject to change in future.


1. New fuel


Power station name Quantity shipped Timing Facility name
Hamaoka Nuclear
Power Station,
Reactor No. 3
172 assemblies Second quarter Nuclear Fuel Industries, Ltd.

2. Spent fuel


Power station name Quantity shipped Timing Facility name
Hamaoka Nuclear
Power Station
Six NFT-38B packages
(228 assemblies,
approx. 39 tons U)
Third quarter Japan Nuclear Fuel Limited spent fuel receiving and storage facility

3. Low-level radioactive waste


Power station name Quantity shipped Timing Facility name
Hamaoka Nuclear
Power Station
135 shipping containers
(1,080 drums)
March 2008 Japan Nuclear Fuel Limited low-level radioactive waste disposal center