Electric Power Generated and Purchased for September and First Half, 2006 (Brief Report)
October 6, 2006
Chubu Electric Power Co., Inc.
Overview of September 2006
- • Electric power generated and purchased by Chubu Electric equaled 98.5% the volume of the same month a year ago, the first year-on-year decline in 14 months. Various factors contributed to this, including less use of air conditioning because of the cooler weather this year than last.
Overview of first half, FY2006
- • Electric power generated and purchased by Chubu Electric equaled 102.3% the volume of the same period a year ago, marking five consecutive year-on-year increases for the period.
1. Electric power generated and purchased
(units: kWh, %)
| September | First half total | |
|---|---|---|
| Electric power generated (% of prev. year) |
12,089,000,000 (98.5) |
71,679,000,000 (102.3) |
| Breakdown: Hydroelectric power (% of prev. year) |
671,000,000 (75.7) |
5,394,000,000 (114.4) |
| Thermal power (% of prev. year) |
9,332,000,000 (125.8) |
50,258,000,000 (114.5) |
| Nuclear power (% of prev. year) |
820,000,000 (31.2) |
8,022,000,000 (55.6) |
| Power purchased from other suppliers, etc. (% of prev. year) |
1,266,000,000 (94.0) |
8,005,000,000 (114.1) |
2. Monthly top three days' average power
(units: 10,000 kW, %)
| September | First half total | |
|---|---|---|
| Top three days' average power (% of prev. year) |
2,476 (97.9) |
2,685 (101.9) |
- *This is the average of the three days with the greatest power supply during the month.
- *The top three days' average power for the first half was set in August.
3. Water yield
(units: %)
| September | First half total | |
|---|---|---|
| Water yield | 76.1 | 98.6 |
- *Water yield = Hydroelectric power produced / Average hydroelectric power produced over past 30 years × 100
- *Expresses degree of water abundance relative to benchmark 100%
4. Nuclear power facility load factor
(units: %)
| September | First half total | |
|---|---|---|
| Nuclear power facility load factor | 22.8 | 36.6 |
- *Hamaoka Nuclear Power Station Reactor
No. 1 operations suspended from Nov. 7, 2001 [periodic inspection from Apr. 26, 2002]
No. 2 operations suspended from Feb. 21, 2004 [periodic inspection from Feb. 21, 2004]
No. 3 operations suspended from July 21, 2006 [periodic inspection from July 21, 2006]
No. 5 operations suspended from June 15, 2006