Chubu Electric Wind Power Station Development Plan
September 28, 2007
Chubu Electric Power Co., Inc.
As part of its initiatives to solve global environmental problems, Chubu Electric is developing and implementing commercial wind power.
We have recently formulated plans to develop wind power along the coast in Omaezaki City, Shizuoka Prefecture. This is our second development plan in Omaezaki City following plans announced in November of last year. Chubu Electric looks forward to working with the local population and institutions of this area as we develop these plans.
We will continue to implement wind and other alternative energy sources as we seek solutions to global environmental problems.
< Development plan overview >
| Development plan (current portion) |
Preceding development plan in Omaezaki City (previously announced) |
|
| Location | Omaezaki City, Shizuoka Prefecture | Omaezaki City, Shizuoka Prefecture |
| Scale of development plan | 16,000 kW (2,000kW × 8units) |
8,000 kW (2,000kW × 4units) |
| Anticipated annual power generation | Approx. 40,000 MWh | Approx. 20,000 MWh |
| Start of operations | June 2010 | February 2009 |
< Reference >
Site location

Overview of a wind turbine generator (current plan)