Chubu Electric Power has completed construction of the Atsumi Wind Power Station ("the Power Station") in Tahara City, Aichi Prefecture and the Power Station commenced commercial operation on September 2.
This is our second onshore wind power station, following the Omaezaki Wind Power Station in Omaezaki City, Shizuoka Prefecture.

We appreciate the cooperation and understanding of the local community and relevant parties in the construction of the Power Station.

The Chubu Electric Power Group has positioned renewable energy as one of its main power sources that will contribute to achieving a carbon-free society as well as enhancing energy self-sufficiency, and we will continue active development in order to achieve our goal of "an expansion over 3.2 million kW through ownership, construction, and maintenance of renewable energy plants by around 2030".

[Overview of Atsumi Wind Power Station]

Location of the Station

Konakayama-cho and surrounding areas, Tahara City, Aichi Prefecture (on the premises of the JERA Atsumi Thermal Power Station)

Power output

7,400 kW (2 units)

Estimated annual power output

Approximately 19 million kWh(equivalent to power for approximately 6,000 ordinary households)

Construction start date

December 13, 2021

Commercial operation start date

September 2, 2023