Appropriation of procured funds(As of March 31, 2022)

Item Amount
Procurement amount (amount received) 9.9 billion yen
Appropriated amounts 9.9 billion yen
(breakdown) Kurokawadaira Hydro Power (Nagano Pref.) 0.1 billion yen
Ichishiro Hydro Power (Shizuoka Pref.) 0.1 billion yen
Seinaiji Hydro Power (Nagano Pref.) 1.9 billion yen
Abekawa Hydro Power (Shizuoka Pref.) 2 billion yen
Yokkaichi Biomass (Mie Pref.) 5.4 billion yen
Atsumi Onshore Wind Power (Aichi Pref.) 0.1 billion yen
Unappropriated balance Not applicable

*1 Figures less than the expressed unit are rounded down.

*2 Of the amount procured, 5.9 billion yen was allocated to the refinancing of the construction funds for the Yokkaichi Biomass Power Plant and the Seinaiji Hydroelectric Power Plant.

Environmental improvement effect(April 2021-March 2022)

Project Installed
capacity
Amount of CO2
emission reductions
Kurokawadaira Hydro Power (Nagano Pref.) 0.2 MW 141,572(t-CO2/y)
Yokkaichi Biomass (Mie Pref.) 49.0 MW

*1 Annual CO2 emission reduction calculation method: FY2021 annual power generation volume (MWh) x CO2 emission coefficient (t-CO2/MWh)

*2 As of March 31, 2022, the Ichishiro Hydro Power Station, Seinaiji Hydro Power Station, Abekawa Hydro Power Station, and Atsumi Onshore Wind Power Station listed in the allocation of procured funds are currently under construction. The environmental improvement effects will be reported after the start of operations.