Mid-Term Outlook Major Power Source Development Plan

Internally-generated Power

(MW)

Type FY2018(Actual) FY2019 FY2020-FY2023 FY2024-FY2028
Nuclear Does not apply Does not apply Does not apply Does not apply
Thermal Owase Unit 1,3
(December 2018)
-875

Yokkaichi Unit 3
(December 2018)
-220



Does not apply Taketoyo 5
(March 2022)
1,070
Does not apply
Hydro Takeshi*
(November 2018)
0.02

Miho*
(January 2019)
0.3
Does not apply Seinaiji
(June 2022)
5.6

Kurokawadaira
(June 2021)
0.17

Ichishiro
(March 2022)
0.16
Abekawa
(December 2024)
7.5
Renewable energy
Wind
Does not apply Does not apply Atsumi
(FY2021)
7.4
Does not apply
Renewable energy
Solar
Does not apply Does not apply Does not apply Does not apply
Renewable energy
Biomass
Does not apply Does not apply Biomass power generation facility at Yokkaichi
(April 2020)
49
Does not apply

(Note) Facilities for which the date of commencement of operation is undecided are not included.
* Output increase from facility improvement, etc.