Press Release
Goto Floating Wind Farm LLC Consortium Begins Offshore Wind Turbine Assembly - Towards Realization of Floating Offshore Wind Power Generator -
October 07, 2022
Goto Floating Wind Farm LLC
TODA CORPORATION
ENEOS Corporation
OSAKA GAS CO., LTD.
INPEX CORPORATION
Kansai Electric Power Co., Inc.
Chubu Electric Power Co., Inc.
Goto Floating Wind Farm LLC (the Consortium) announced today the first of eight floating wind turbine units for the Goto City Offshore Wind Power Generation Project has been completed and loaded onto the semi-submersible spud barge(Note 1) Float Raiser at the pier yard in Fukue Port, Goto City, Nagasaki Prefecture, Japan. The floating wind turbine unit is scheduled to depart Fukue Port on Saturday October 8, 2022, en route to a location offshore Kabashima to initiate wind turbine assembly work.
(Note 1) A large barge for loading floating offshore wind turbines built onshore and floating and launching these offshore in a semi-submersible state
Since April 2022, the Consortium has been following the approval procedure for the exclusive use of sea zones, etc., a requirement for the installation of power generation infrastructure. This follows the Consortium being awarded Japan’s first public offering plan certification as an offshore wind power generation facility to be constructed based on the Act of Promoting Utilization of Sea Areas in Development of Power Generation Facilities Using Maritime Renewable Energy Resources.
The Consortium will pursue the construction of a floating offshore wind farm within the designated area, aiming to start commercial operations in January 2024.
Floating wind turbine unit being loaded
Completion of loading
Attachments
Attachments1
Attachments
【Business summary】
Project title |
Goto City Offshore Wind Power Generation Project |
---|---|
Operator |
Goto Floating Wind Farm LLC |
Power generation facility |
Floating offshore wind power generation facility 16.8 MW (= 2.1 MW machine x 8 units) (Total length 176.5m, rotor diameter 80m) |
Headquarters |
Goto City, Nagasaki Prefecture, Japan |
Start of operations |
January 2024 (Scheduled) |
Shareholders |
TODA CORPORATION |
Rendering of project upon completion
【Profiles of Consortium Member Companies】
TODA CORPORATION
Established |
January 1881 |
---|---|
Representative |
Otani Seisuke, President and Representative Director |
Head Office |
8-5 Hatchobori 2-Chome, Chuo-ku, Tokyo, Japan |
Business Areas |
|
ENEOS Corporation
Established |
May 1888 |
---|---|
Representative |
Saito Takeshi , Representative Director, President |
Head Office |
1-1-2 Otemachi, Chiyoda-ku, Tokyo, Japan |
Business Areas |
|
OSAKA GAS CO., LTD.
Established |
April 1897 |
---|---|
Representative |
Fujiwara Masataka, Representative Director and President |
Head Office |
4-1-2 Hirano-machi, Chuo-ku, Osaka |
Business Areas |
|
INPEX CORPORATION
Established |
April 2006 |
---|---|
Representative |
Ueda Takayuki, Representative Director, President & CEO |
Head Office |
Akasaka Biz Tower, Akasaka 5-3-1, Minato-ku, Tokyo |
Business Areas |
In addition to the exploration, development, production and marketing of petroleum, natural gas and other mineral resources in Japan and other countries, INPEX is actively endeavoring to develop renewable energies, hydrogen energy, carbon dioxide capture and storage (CCS) technology, methanation technology and other new technologies. |
The Kansai Electric Power Co., Inc.
Established |
May 1951 |
---|---|
Representative |
Mori Nozomu, Director, Representative Executive Officer, President |
Head Office |
3-6-16 Nakanoshima, Kita-ku,Osaka |
Business Areas |
Electric power, heat supply, telecommunications, gas supply, etc. |
Chubu Electric Power Co., Inc.
Established |
May 1951 |
---|---|
Representative |
Hayashi Kingo, President & Director |
Head Office |
1, Higashi-shincho, Higashi-ku, Nagoya, Aichi |
Business Areas |
Renewable energy business, overseas business, community support infrastructure related business, etc. |