Press Release

Press Release

Omaezaki Port Biomass Power Plant Started Commercial Operation

February 05, 2025
Chubu Electric Power Co.,Inc.

Omaezaki Port Biomass Energy LLC, a limited liability company jointly owned by Chubu Electric Power Co., Inc., RENOVA, Inc., Mitsubishi Electric Financial Solutions Corporation, and Suzuyo Shoji Co., Ltd., has completed construction of the Omaezaki Port Biomass Power Plant (the "Plant") and commenced commercial operation on January 29, 2025.

The Plant is a wood-fired biomass power plant with an output of 74,950 kW, and is expected to generate approximately 530 million kWh per year.

We appreciate the cooperation and understanding of the local community and relevant parties in its construction.

The Chubu Electric Power Group has positioned renewable energy as one of its main power sources that will contribute to achieving a carbon-free society as well as enhancing energy self-sufficiency, and we will continue active development in order to achieve our goal of "an expansion over 3.2 million kW through ownership, construction, and maintenance of renewable energy plants by around 2030".

Panoramic View of Omaezaki Port Biomass Power Plant

Panoramic view of the Plant

Overview of Omaezaki Port Biomass Power Plant

Plant location

6620-78, Minato, Omaezaki, Shizuoka Prefecture, Japan

Power output

74,950kW

Estimated annual power output

Approx. 530 million kWh (equivalent to the annual electricity consumption of approximately 170,000 general households)

Fuel type

Wood pellets, palm kernel shells

Start of construction

April 1, 2021

Start of operation

January 29, 2025

Overview of the project

Operating company

Omaezaki Port Biomass Energy LLC

Headquarters

6620-78, Minato, Omaezaki, Shizuoka Prefecture, Japan

Representative

Hitoshi Nishimura

Shareholding company

RENOVA, Inc. (38%),Chubu Electric Power Co., Inc. (34%), Mitsubishi Electric Financial Solutions Corporation (18%), Suzuyo Shoji Co., Ltd.(10%)