Press Release

Press Release

Start of Construction on the Taketoyo Thermal Power Station Unit 5

April 18, 2018
Chubu Electric Power Co.,Inc.

Chubu Electric Power would like to announce that it has started construction on the Taketoyo Thermal Power Station Unit 5 today.

As a high efficiency coal-fired thermal power plant, Taketoyo Thermal Power Station Unit 5 will supply electricity stably in the long-term and cut down on power generation costs while striving to reduce the burden on the environment by mixing woody biomass into coal as fuel and adopting a high efficiency exhaust gas processing device.

With the continued cooperation and understanding of the local community and related parties, we will proceed with construction putting safety first.

[Overview of Taketoyo Thermal Power Station Unit 5]

Location 

1-1, Ryugu, Taketoyo Town, Chita-gun, Aichi Prefecture

 Output

1,070,000kW

 Power generation method

Steam power generation

 Fuel

Coal and woody biomass

 Thermal efficiency

46% (lower heating value standard level)

 Start of commercial

Scheduled to start in March 2022