Hamaoka Nuclear Power Station Units 1 and 2 Entering Decommissioning Phase 3

December 18, 2024
Chubu Electric Power Co.,Inc.

On December 18, the Nuclear Regulation Authority approved our application for approval of changes to the decommissioning plan (Note 1) for Units 1 and 2 of the Hamaoka Nuclear Power Station ("decommissioning plan"), submitted on March 14, 2024, as partially amended on July 26, November 12 and December 3, 2024, and our application for approval of changes to the Technical Specification for the Nuclear Reactor Facility (Note 2), submitted on June 6, 2024, as partially amended on December 3, 2024.
Upon receiving these approvals, we will start internal procedures to implement the decommissioning of Hamaoka Nuclear Power Station Units 1 and 2, which will be shifted to Phase 3 of the decommissioning process on December 25.
We will prepare a detailed work plan based on the approved decommissioning plan and Technical Specification, and proceed with the dismantling work under a fully organized structure once the site work is ready.

Application for Approval of Change Outline

1 Decommissioning plan

(1)Concretization of dismantling work in Phase 3

  • Concrete dismantling methods for core internals, reactor pressure vessels, reactor containment vessels, etc.
  • Reflect the results of the assessment of exposure from dismantling work

(2)Change in decommissioning schedule

  • The schedule for Phase 3 was changed from 6 to 12 years.

(3)Others

2 Technical Specification for the Nuclear Reactor Facility

(1)Addition of storage areas designated for dismantled materials, etc. and storage management measures

(2)Change in the target control value for the release of radioactive gaseous waste

(3)Appropriateness of description
(Press release issued on June 6, 2024) 
(Partial amendment announced on December 10, 2024)

Chubu Electric Power will steadily proceed with the decommissioning of Units 1 and 2, placing the highest priority on safety and ensuring transparency.

(Note 1) The decommissioning plans for Units 1 and 2 of the Hamaoka Nuclear Power Station stipulate the overall plan for the safe and reliable dismantling of the reactor facilities of Units 1 and 2, as well as the details of the work to be performed and safety assurance measures to be taken in the decommissioning process. The decommissioning of Units 1 and 2 will be conducted in four phases, from Phase 1 "Preparation Period for Dismantling" to Phase 4 "Period of Dismantlement of Buildings, etc."
(Note 2) Based on the Act on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors, the Technical Specification for the Nuclear Reactor Facility stipulates the items (safety organizations, safety measures, etc.) to be observed by the nuclear reactor installer in the safe operation and decommissioning of the nuclear power plant.