Press Release
Commencement of Abekawa Hydroelectric Power Station Construction
July 13, 2020
Chubu Electric Power Co.,Inc.
Chubu Electric Power is proud to announce that today we commenced construction of the Abekawa Hydroelectric Power Station as part of our efforts to further expand renewable energies.
The Abekawa Hydroelectric Power Station is a run-of-the-river power station that will be capable of generating 7,500 kW. We plan to place the plant in service in December 2024.
Continuing to embrace an eco-conscious mindset, we will proceed to construct the facility while affording the highest priority to safety and with the understanding and cooperation of local residents as well as other relevant parties.
[Overview of Planned Abekawa Hydroelectric Power Station]
Name of station |
Abekawa Hydroelectric Power Station |
---|---|
Location |
Nyujima, Umegashima and Utogi districts in Aoi-ku, Shizuoka City, Shizuoka Prefecture |
River system/river name |
Abekawa River System and Abekawa River |
Power output |
7,500kW |
Maximum water consumption |
7.00m3/s |
Effective head |
Approx. 123m |
Estimated annual power output |
Approximately 39,000 MWh (equivalent to the annual electricity consumption of approx. 12,500 average households) |
Amount of reduced CO2 emissions |
Approximately 17,900 tons annually |
Scheduled start of operation |
December 2014 |