Press Release
Development of a Wood-fired Biomass Power Plant with an Output of 1990 kW in Yahaba Town, Shiwa District, Iwate Prefecture ~Aiming to Commence Operation in January 2026 ~
June 27, 2023
Chubu Electric Power Co.,Inc.
Inabata & Co., Ltd.
Furusato Mokuzai Logistics K. K.
Chubu Electric Power Co., Inc. ("Chubu Electric Power”) and Inabata & Co., Ltd. (“Inabata”) reached an agreement with Furusato Mokuzai Logistics K. K. (“Furusato Mokuzai Logistics”) to invest in Furusato FIC Energy, LLC (“Project Company”), established by Furusato Mokuzai Logistics, and to develop the Yahaba Power Plant (“this power generation business project”). Today, the Project Company exchanged a Memorandum on Supplying Electricity During Natural Disasters with Yahaba Town and a Memorandum on Creating a Basic Plan Stipulated in the Act on Promoting Generation of Electricity from Renewable Energy Sources Harmonized with Sound Development of Agriculture, Forestry and Fisheries with Yahaba Town and Tohoku Bank, Ltd.
This power generation project aims to build and operate a wood-fired biomass plant in Yahaba Town, Shiwa District, Iwate Prefecture. It will have an output of 1990 kW and will be fueled with mainly unused timber harvested in thinning and lumber left in forests (Note) from Iwate Prefecture.
(Note) Lumber harvested as part of forest management and wood production processes but left unused in forests
The three incorporated companies and the project company will carry out development of this plant with the understanding and cooperation of the local community and other related parties.
[Illustration of Completed Plant]
[Overview of the Project]
Location of the power plant |
2-78-1, Kemuyama, Yahaba Town, Shiwa District, Iwate Prefecture |
---|---|
Power output |
1,990kW |
Estimated annual power output |
Approx. 14.5 million kWh (equivalent to power consumed by 5,000 average households) |
Fuel type |
Wood chips (mainly unused timber generated in thinning and lumber left in forests in Iwate Prefecture) |
Construction start date |
April 2025 |
Scheduled start of operation |
January 2026 |
Investment |
Chubu Electric Power, Inabata, Furusato Mokuzai Logistics |
[Company Profiles]
Furusato FIC Energy, LLC
Established |
May 2022 |
---|---|
Location |
6-37-1, Higashi-mirumae, Morioka City, Iwate Prefecture |
Representative |
Executive Manager Tadashi Hatakeyama (Furusato Mokuzai Logistics) |
Business |
Development, construction, operation, maintenance management of biomass power generation facilities |
Chubu Electric Power Co., Inc.
Established |
May 1951 |
---|---|
Location |
1 Higashi-shincho, Higashi-ku, Nagoya-shi, Aichi Prefecture |
Representative |
President & Director Hayashi Kingo |
Business |
Renewable energy projects, overseas projects, community support infrastructure-related projects, etc. |
Inabata & Co., Ltd.
Established |
June 1918 |
---|---|
Location |
1-15-14, Minami-senba, Chuo Ward, Osaka City, Osaka Prefecture |
Representative |
Representative Director and President Katsutaro Inabata |
Business |
Retail and manufacturing of information electronics, chemicals, living essentials, plastics |
Furusato Mokuzai Logistics K. K.
Established |
April 2011 |
---|---|
Location |
6-37-1, Higashi-mirumae, Morioka City, Iwate Prefecture |
Representative |
Representative Director Tadashi Hatakeyama |
Business |
Timber transportation, wood chip processing, wood production, etc. |