Press Release

Press Release

Development of AI-based Hydropower Planning Support System and Patent Application

December 15, 2023
Chubu Electric Power Co.,Inc.
TSUNAGU Community Analytics Co., Inc.

Chubu Electric Power Co., Inc. (President & Director: Kingo Hayashi; "Chubu Electric Power") and TSUNAGU Community Analytics Co., Inc. (President: Osamu Kuribayashi; "TCA") have developed a system that uses AI to support optimal power generation planning at hydroelectric power plants and yesterday jointly filed a patent application for the AIs incorporated in the system.

Chubu Electric Power is working to increase power generation from existing power sources as well as developing new power sources in order to realize a decarbonized society. For hydroelectric power generation, Chubu Electric Power aims to maximize power generation by improving the accuracy of forecasting water inflow into dams through the promotion of DX and by operating with an optimal power generation plan.
In addition, power generation plans for hydroelectric power plants have been currently prepared by skilled employees, who spend about half a day based on their experience and know-how, causing issues to improve operational efficiency and train younger employees.

The system enables to simultaneously optimize the power generation operations of multiple hydroelectric power plants where water flows in and out of different rivers, which consists of the three AIs listed below.

(1) Inflow Forecasting AI: Predicts the amount of water inflow into the dam based on the next day's forecast rainfall.
(2) Historical Search AI: Searches for past power generation plans under similar conditions based on conditions such as dam water levels and available water volume on the following day.
(3) Optimization Calculation AI: Creates power generation plans based on conditions such as predicted inflow at each dam, dam water levels, and power generation operation constraints to meet objectives such as maximum power generation and maximum power sales.

Chubu Electric Power and TCA have together conducted the verification at hydroelectric power plants under Chubu Electric Power's service area in the Hida River system, which has a particularly complex configuration, from April 2021. As a result, it is confirmed an annual power increase of approximately 2% (up to approximately 30 million kWh/year for the entire water system, equivalent to the annual power consumption of approximately 10,000 standard households) can be expected through operation based on the power generation plan formulated using the system.

It is also possible to reduce the time required to develop power generation plans to less than a quarter of the conventional time by utilizing the system, significantly improving efficiency. Furthermore, the system will enable the training of young employees, which until now has mainly involved on-the-job training, to acquire skills in a short period of time through simulations using the system.

Starting with full-scale operation in the Hida River system in FY2024, the two companies will continue to introduce the system into other water systems, thereby contributing to the realization of a decarbonized society by continuously working to increase the amount of electricity generated by hydropower without emitting CO2.

Attachment

Attachment1

Overview of AI-based hydropower planning support system

1. Dam inflow prediction by Inflow Forecasting AI

By learning the relationship between past rainfall and water inflow to dams, the AI predicts the inflow to each dam based on predicted rainfall for the following day.

2. Next-day power generation planning proposal by Historical Search AI

Based on various conditions such as the water level of each dam on the following day and the amount of water available based on the water storage plans of each dam, the AI searches for days with similar conditions from past data to create a draft power generation plan for the following day that reproduces past operations.

3. Next-day power generation planning proposal based on Optimization Calculation AI

The AI creates a theoretically optimal power generation plan for the following day for each objective of maximizing the amount of electricity sold, maximizing the amount of electricity generated, and minimizing the amount of overflow, based on various conditions such as the predicted inflow at each dam, dam water levels, and power generation operation constraints.

4. Determination of next day power generation plan

The operator determines the power generation plan for the next day of actual operation by referring to the plans created by "Historical Search AI" and "Optimization Calculation AI".

<Reference>Outline of TSUNAGU Community Analytics

Company Name

TSUNAGU Community Analytics Co., Inc.

Representative

Osamu Kuribayashi, President and Representative Director

Headquarters

4-5-3 Sakae, Naka-ku, Nagoya City

Capital

200 million yen (including capital reserve)

Investment

Chubu Electric Power 70%, Chuden CTI 20%, Chubu Electric Power Grid 5%, Chubu Electric Power Miraiz 5%

Established

February 16, 2021

Business Activities

  • Data analysis business
  • Consulting business for data utilization
  • Data analysis human resource development business
  • Businesses related to the above and all accompanying operations

Website

TSUNAGU Community Analytics Co., Inc. website

Go to the Top of the Page