Press Release

Press Release

Changes, etc. in the Transporting Schedule for New Fuel, etc. for FY2011 at Hamaoka Nuclear Power Station

October 26, 2011
Chubu Electric Power Co.,Inc.

This announcement is to notify that the schedule for transporting spent fuel that was under consideration in the "Transporting Schedule for New Fuel, etc. for FY2011 at Hamaoka Nuclear Power Station" announced by Chubu Electric Power on March 31, 2011 has been settled, and that the schedule for transporting new fuel (also outlined in the March 31 announcement) has been changed.

("Transporting Schedule for New Fuel, etc. for FY2011 at Hamaoka Nuclear Power Station" announced on March 31, 2011)

1 Spent fuel

Power plant name

Quantity shipped

Period of shipment

Transporting company

Hamaoka Nuclear Power Station

NFT-38B x 1package
(38 assemblies,About 7 ton U)
NFT-12B x 1 package
(12 assemblies, about 2 ton U)

Fourth quarter

Japan Nuclear Fuel Limited
Spent Fuel Receiving and
Storage Facility

2 New fuel

In consideration of the shutdown of all units at the Hamaoka Nuclear Power Station, all plans for importing new fuel for the current fiscal year have been withdrawn.

In addition, during the receiving inspections conducted in FY2010, one assembly of new fuel was confirmed to have incorrectly installed parts, and was returned to the fuel manufacturer for repair.

Power plant name

Quantity shipped

Period of shipment

Receiving facility

Hamaoka Nuclear Power Station Unit 3

1 assembly

Fourth quarter

Areva NP

Go to the Top of the Page