Start of Commercial Operation of Joetsu Thermal Power Station Unit 1-1

July 01, 2012
Chubu Electric Power Co.,Inc.

Chubu Electric Power began construction on the Joetsu Thermal Power Station in Joetsu City, Niigata Prefecture in March 2007, and work has proceeded smoothly since then.

This is to announce that Unit 1-1, the first unit at the power station, began commercial operation at 16:00 today.

Attachment

Attachment1

Overview of the Joetsu Thermal Power Station

Location

2, Yachiho, Joetsu City, Niigata Prefecture

Output

Group No. 1 (Units 1-1 and 1-2)
1,190 MW (595 MW × 2 blocks)

Group No. 2 (Units 2-1 and 2-2)
1,190 MW (595 MW × 2 blocks)

Power generation method

Multi-shaft combined-cycle power generation method (1,300°C class improved gas turbines)

Start of construction

Group No. 1 March 2007

Unit 2-1        April 2008

Unit 2-2        February 2010

Planned start of commercial operation

Unit 1-1   July 01, 2012

Unit 1-2   January 2013

Unit 2-1   July 2013

Unit 2-2   May 2014

Characteristics

First thermal power station outside our service area

This is Chubu Electric Power's first thermal power station located on the Sea of Japan side of the country, outside our service area.

Power generation facility with high efficiency and low environmental burden

The power station will achieve thermal efficiency of at least 58%, the highest level in Japan, thanks to the multi-shaft combined-cycle power generation technology using 1,300°C class improved gas turbines.

This will allow us to use limited energy resources more effectively while reducing CO2 emissions.

In addition, the use of clean LNG as fuel eliminates soot.

High degree of automation

The facility is built to be controlled and monitored, from startup to shutdown, by a small number of workers in a central control room.