Press Release
Start of Construction for the "Nyukawa Hydroelectric Power Station"
March 20, 2015
Chubu Electric Power Co.,Inc.
Chubu Electric Power would like to announce that we submitted a starting notification for the new construction of "Nyukawa Hydroelectric Power Station", based on the River Act , to Gifu Prefecture. The work has begun today.
Nyukawa Hydroelectric Power Station is a regular water-flow release hydroelectric power station scheduled for construction directly below the Nyukawa Dam owned by Gifu Prefecture and Takayama City. The dam effectively utilizes dam head and released water in order to maintain the river environment.(Notification complete as of November 27, 2012)
Maximum output is 350kW, and operation is planned to begin in June, 2016.
We shall be grateful for the understanding and cooperation of Gifu Prefecture and Takayama City, local residents and other parties concerned as we proceed with the construction regarding safety as the top priority.
[Overview of plan]
Name of station |
Nyukawa Hydroelectric Power Station |
---|---|
Location |
Nyukawa-cho, Takayama City, Gifu Prefecture |
Name of dam |
Nyukawa Dam |
Dam owners |
Gifu Prefecture and Takayama City |
Output |
0.35MW |
Projected annual electricity output |
2,100MWh (equivalent to annual electricity consumption of approx. 580 average households) |
Reduction in CO2 emissions |
Approx. 1,100 tons per year |
Planned start of commercial operation |
June 2016(scheduled) |